PVC plants in China to undergo maintenance in April-July 2017

by ChemOrbis Editorial Team - content@chemorbis.com
  • 29/03/2017 (10:31)
A source from a Chinese producer reported that several ethylene and acetylene based PVC plants in the country will be shut for maintenances in the April-July period.

Wuhai Chemical is planning to shut its acetylene-based PVC unit in early April for turnaround. The 300,000 tons/year PVC unit is expected to be offline for around a week.

Inner Mongolia Junzheng Chemical is planning to shut its acetylene-based PVC plant in mid-April for maintenance. The 380,000 tons/year plant is expected to remain offline for 7 to 10 days.

Ningxia Jinliyuan will have shutdown maintenance at its acetylene-based PVC plant with 250,000 tons/year production capacity in mid-April for a week.

Yibing Tianyuan will shut its PVC plant with a production capacity of 400,000 tons/year in late April for a week.

Shanxi Jin Tai’s acetylene-based PVC plant with a production capacity of 300,000 ton/year of PVC will be shut in late April for a week.

Inner Mongolia Yihua Chemical Industry Co.’s acetylene-based PVC plant in Inner Mongolia with 400,000 tons/year production capacity will undergo maintenance in April. Further detail regarding the shutdown is yet to known.

Meanwhile, Inner Mongolia Yili Chemical Industry Co Ltd will shut its acetylene-based PVC plant either in the end of March or in the end of April for turnaround which is expected to last for 7 to 10 days.

Xinjiang Tianye, a major acetylene-based PVC producer, will also shut its PVC plant in May for 20 days. The plant has a production capacity of 1.4 million tons/year.

Anwei Huasu acetylene-based PVC plant with a production capacity of 460,000 tons/year will be shut in May for 10 days.

Henan Shengma will also shut its 300,000 tons/year plant in late March for a week.

Yidong Dongxin will shut its acetylene-based PVC plant in late May for 8 to 10 days. The acetylene-based PVC plant has a production capacity of 300,000 tons/year.

Zhongyan Jilantai’s 400,000 tons/year capacity of acetylene-based PVC plant will undergo maintenance in June for 15 days.

Qilu Petrochemical will shut its 230,000 tons/year ethylene based PVC plant from mid-May to June.

Tianjin Bohai Chemical’s 400,000 tons/year capacity ethylene based PVC plant will be shut in July for a week.