Sasol’s Lake Charles project faces more delays
The company stated that the LCCP, consisting of a world-scale ethane cracker and six downstream units, experienced major cost overruns due to several factors, within and beyond the control of management.
Sasol stated that scope additions and productivity losses stemming from public holidays and inclement weather have resulted in an increase in the project’s overall costs.
As part of the updated schedule, the start-up of the 1.5 million tons/year cracker has been delayed until August and LDPE plant will start operations in July, instead of the previously announced March.
Sasol also announced that the new LLDPE unit produced its first product in January this year and beneficial operation is expected within the current month.
More free plastics news
Plastic resin (PP, LDPE, LLDPE ,HDPE, PVC, GPS; HIPS, PET, ABS) prices, polymer market trends, and more...- March hints at further hikes in European PP, PE markets
- India’s PVC market dips to new lows on Taiwan’s March cuts, players seek signs of bottom
- Q1 turnarounds uplift Mid-East PP, PE markets in February; will it spill over to March?
- SE Asia’s indefinite PE shutdowns: A market in crisis as demand woes threaten survival
- Türkiye’s PPH markets perform better than copolymers in February
- Margin recovery priorities outweigh supply imbalances in European PVC markets
- Asian PVC demand stagnant; recovery hopes shift to end of Q1
- Tough slog in S Korea’s petchem industry spells disappointing 2024 financial results; will government's recent plan help weather the storm?
- China’s PP, PE markets face post-holiday supply surge and tepid demand
- A tug-of-war unfolds in Türkiye as PVC demand struggles against rising costs