Update on Thailand’s PTT’s PE production lines

by ChemOrbis Editorial Team - content@chemorbis.com
  • 23/03/2015 (11:42)
A source close to Thailand’s PTT reported that the producer restarted its LDPE line at the beginning of March after conducting a 12-day scheduled turnaround. The line is able to produce 300,000 tons/year of LDPE.

The source added that PTT has postponed the maintenance date of its HDPE plant from March to late April. The 300,000 tons/year plant will remain offline for 15 days. The company is planning to resume operations by mid-May.

Meanwhile, the producer is also planning to shut its 400,000 tons/year LLDPE plant once they restart their HDPE plant.